Joint details roof floor truss manual 7 31 08 10 43 am page 11.
Floor truss strongback detail.
They should be securely.
Top chord bearinga floor truss support condition in which the truss load is transferred to the bearing or support through the top chord and 4x4 block end detail.
2x6 strongback is recommended located every 8 to 10 feet along a floor truss.
Standard repair detail for missing section of top or bottom chord.
Standard repair detail for notching cutting of chords of floor gables ladder trusses.
Floor truss repair details.
For instance can three trusses of a type be tied together by strongbacks then the next series of different trusses be tied together without.
Non structural gable stud attachment.
It serves to make the floor more comfortable for those living and working in a structure.
Top chord bearing end condition the ultimate advantage probably one of the most appreciated feature of the mitek floor truss engineered floor system is the ability to hide beam in the floor by using a.
Mitek floor truss system design flexibility allow a multitude of pre fabricated details that substantially speed up the installation on site.
Strongback installation detail strongback bridging is an excellent and inexpensive way to improve the overall rigidity of the floor system and eliminate vibration.
Field peak cap connection detail.
When the 4x4 block length is extended this is referred to as mid chord bearing.
Truss a pre built component that functions as a structural support.
Floor truss bearing detail.
Roof truss repair details.
Floor truss bearing detail.
Contact mitek engineering support for any questions.
Typical splice 4 0 0 attach to chord with two 12 x 3 wood screws 216 diam insert screw through outside face of chord into edge of strongback do not use drywall type screws insert wood screw through outside face of chord into edge of strongback.
Can the strongback bracing end at a truss without tying into an end wall.
Standard repair detail for missing section of top or bottom chord.
If you need a pathway across the strongback for an hvac or plumbing run you can cut the strongback making sure that no less than 3 joists are connected per strongback segment.
Strongback supports cantilever and jack details lateral bracing suggestions 2x6 strongback lateral supports should be located on edge approximately every 10 feet along the floor truss.
Deep residential floor system with trusses in lengths up to 19 ft.
Some of these standard details may be sealed upon request.
View the following detail guides.
I am looking for strongback bracing requirements for a 12 in.
Ok back to the question.